ELECTRIC HOTCAKES: Let’s talk about gas turbines. After semiconductors, they are arguably the most important bit of machinery in the artificial intelligence boom.
But like chips, turbines are in short supply amid hyperscalers’ rush to secure electrons. That has sent their price tag soaring and raised questions over who will pay the bill.
The answer has major political ramifications in capitals on both sides of the Atlantic.
Consider a seemingly mundane regulatory filing in Kentucky last week, where a local utility submitted an application to build a new combined-cycle natural gas plant needed to power a data center. Its price tag: a cool $2.81 billion, according to regulatory filings.
With a listed generating capacity of 769 megawatt, that works out to about $3,650 per kilowatt, according to analysts at the research outfit Halcyon.
That is an “eye-popping” number, said Kent Chandler, a former chair of the Kentucky Public Service Commission.
“That figure should worry every public utility commissioner in the country,” he said. “These things are material inputs into the cost of electricity, no matter where you are.”
As recently as 2023, the median combined-cycle plant cost roughly $1,400 per kilowatt to build, according to Halcyon’s gas plant tracker. It now estimates that number is around $2,300 per kilowatt.
Such escalating costs are part of the reason U.S. politicians are so focused on making data centers pay for their grid upgrades.
In the Kentucky example, the local utility argues that data center operator TeraWulf will pay for the new gas plant and a $285 million substation. The deal calls for $100 million in residential winter bill credits, and will save consumers more than $500 million over the course of TeraWulf’s 20-year power contract, said Kentucky Power spokesperson Sarah Lynch.
“TeraWulf will pay carrying costs during construction of the project and cover any increase in overall generation costs through its rates,” she said.
But the utility plans on owning the plant, raising questions about whether consumers could be on the hook for its costs, said Chandler, who now serves as the vice president of electricity at the Lighthouse Energy Institute. He called it “the first real test” of Kentucky’s attempts to shield ratepayers from the cost of data centers’ grid upgrades.
The project could provide much needed economic development to eastern Kentucky, an impoverished region of the state, but only if the proper protections are in place, he said.
But what happens in Kentucky doesn’t stay there, even if regulators put all the necessary protections in place. The run-up in equipment costs is a global phenomenon — and has the potential to make electricity more expensive for consumers around the world, as higher equipment costs feed into bills.
In Thailand, a plan to expand an existing gas plant was scrapped last year amid a tripling in turbine costs. When German policymakers went out to bid for new gas generation this year, they raised the cap on the maximum bid price by 40% in an attempt to attract more interest from developers. While an East German utility pledged to convert its old coal plants to gas for less than the cap, prices are expected to rise in the second round of bidding — when bigger and more expensive projects will likely dominate.
Rystad Energy, a consulting firm, estimates prices for heavy-duty gas turbines increased 35-40% in the last year alone.
The picture in the U.S. is split. States where utilities operate as regulated monopolies can pass rules forcing data centers to pay for upgrades, but states with competitive wholesale markets could see the high price of new power plants “trickle down to the rate payers,” said Anna Seiple, a gas analyst at Halcyon.
“In order to drive new investment, you need to make sure that your power prices are going to match the cost of building these projects,” she said.
Turbine makers have been moving to expand their factory capacity. Rystad estimates global turbine supply capacity will increase 21% over the next two years. Yet turbine-makers have stopped short of building a wave of new factories, instead preferring to expand existing ones. Many rushed to expand production in the wake of America’s fracking revolution, only to see demand peter out.
The high turbine prices could benefit other technologies. Voltus, for instance, recently struck a deal with Google for 1 gigawatt of virtual power plants, essentially providing more power through aggregating small-scale batteries and solar panels than what San Francisco consumes at peak. Southeastern states are likely to focus more on energy efficiency programs as demand rises, Chandler said, noting that is an area where they have struggled in the past.
“I do think that alternatives will start penciling out more as prices rise like this for a particular type of generation,” he said.