Politico: One step closer to fixing data center grid problems?


ORIGINALLY PUBLISHED IN POLITICO’S POWER MOVES NEWSLETTER

The nation’s grid operators are offering federal regulators their ideas for how to streamline — and contain the costs — of connecting data centers to the grid.

Together, the operators manage electricity for more than half of the U.S. population. Their filings this week to the Federal Energy Regulatory Commission come after a year-long process kicked off by Energy Secretary Chris Wright, who asked FERC to come up with rules to handle the new large loads. That prompted the commission to demand that each regional grid draw up strategies.

Forecasted electricity demand is expected to continue to skyrocket in the coming years, driven primarily by new data center projects. To deal with this coming crisis, regional transmission organizations (or RTOs) are suggesting everything from curtailing the facilities’ power in emergencies to charging developers to connect to the grid.

But the proposals land at FERC at a time when many residents, regulators and elected officials are having second thoughts about the rise of artificial intelligence data centers. State officials have imposed limits on developments, while voters this fall backed moratoriums and anti-data center candidates.

“Perhaps FERC will take a slight[ly] different approach when they look at the responses that do come from the RTOs, knowing that there was such a clear signal from consumers that something needs to be done,” Karen Onaran, president and CEO of ELCON, the national trade association for large industrial consumers of electricity, said of the midterms’ impact.

Then there’s the Bipartisan American Affordability and Jobs Act, the Senate’s proposed permitting overhaul, which is expected to be debated on the floor this week.

“Should BAAJA pass in a form similar to what it looks like right now, it could potentially require the [Regional Transmission Organizations] and [Independent System Operators] and FERC to relook at a few of these provisions,” said Jeff Dennis, executive director of the Electricity Customer Alliance, which represents tech companies, as well as residential and industrial customers.

BAAJA would, for example, require utilities to charge cheaper rates for electricity transmission if a big customer agrees to curb their demand when the power grid is under stress. The bill also contains strict cost allocation plans, such as requiring larger data centers to pay for all of the additional costs for the grid work needed to deliver power to their facilities.

The grid operators’ plans touch on these, with pitches to guarantee data centers some power while allowing some megawatts to be curtailed in a crunch. There are also varying financial obligations for the server farms to get electricity in the first place. The PJM Interconnection, which covers the mid-Atlantic states, proposed halving the amount of time it takes to study prospective generation and transmission infrastructure.

If BAAJA passes, its requirements might supersede these proposals from the grid operators, Dennis said.

If the permitting bill fails, the ball will very much be in FERC’s court.

“FERC will be digesting this while BAAJA’s fate is decided. They have substantive overlap,” echoed Devin Hartman, president of the fiscally conservative think tank Lighthouse Energy Institute. “I would imagine FERC might be more assertive in show cause follow through if BAAJA doesn’t pass.”

While FERC began its data-center-centric proceedings under section 206 of the Federal Power Act, the new submissions are largely coming under Section 205 (with FERC’s encouragement). The difference is greater than one, however.

A 206 proposal requires that the submitting party prove both that the status quo is insufficient and that the new pitch would be just and reasonable. In contrast, 205 proposals pass automatically so long as FERC does not deem them to be unjust and unreasonable.

“FERC is going to be looking at these filings not to decide whether they’re the best option,” Dennis said. “The end result of all that is that it’s going to be a more lenient review, and it really does favor approval.”

Read the whole newsletter here.